Construction was originally scheduled to take between 4-6 months. However, we’ve had to adjust that schedule as follows:
Design and permitting complete: 09/30/2023
Lease-up activities begin (for occupancy in March 2024) – February 2024
Construction complete: 03/01/2024
Occupancy begins 03/15/2024
The property is owned by the Sonoma County Community Development Commission and they are working with their non-profit partners, West County Community Services and Burbank Housing Development Corporation, to complete the work to convert the site to permanent supportive housing.